A logistics company operates 800 electric delivery vans across 45 depots. Each van must be charged overnight to meet next-day routes, but grid demand charges during peak hours (4-9 PM) cost 3x the off-peak rate. The fleet manager needs to stagger charging across depots to minimize cost while ensuring all vans hit 80% SOC by 5 AM.
| van_id | depot | soc_pct | charge_rate_kw | grid_price_kwh | plug_in_time | ts |
|---|---|---|---|---|---|---|
| EV-0447 | Depot-ATL-07 | 18 | 0 | 0.28 | 2024-03-15T17:42:00.000Z | 2024-03-15T17:42:14.000Z |
| EV-0312 | Depot-ATL-07 | 71 | 0 | 0.28 | 2024-03-15T17:38:00.000Z | 2024-03-15T17:42:14.000Z |
| EV-0189 | Depot-DFW-03 | 44 | 7.2 | 0.31 | 2024-03-15T17:15:00.000Z | 2024-03-15T17:42:14.000Z |
| EV-0623 | Depot-DFW-03 | 12 | 19.2 | 0.31 | 2024-03-15T16:55:00.000Z | 2024-03-15T17:42:14.000Z |
| EV-0091 | Depot-ORD-12 | 63 | 0 | 0.24 | 2024-03-15T17:30:00.000Z | 2024-03-15T17:42:14.000Z |
| EV-0558 | Depot-ORD-12 | 37 | 11.5 | 0.24 | 2024-03-15T17:10:00.000Z | 2024-03-15T17:42:14.000Z |
CREATE MATERIALIZED VIEW charge_priority AS
SELECT
ct.van_id,
ct.depot,
ct.soc_pct AS current_soc,
r.required_kwh,
r.departure_time,
(80 - ct.soc_pct) * r.battery_capacity_kwh / 100.0 AS kwh_needed,
EXTRACT(EPOCH FROM r.departure_time - NOW()) / 3600 AS hours_until_departure,
CASE
WHEN ct.soc_pct < 20 THEN 'P1_CRITICAL'
WHEN ct.soc_pct < 40 THEN 'P2_URGENT'
WHEN ct.soc_pct < 60 THEN 'P3_STANDARD'
ELSE 'P4_DEFERRABLE'
END AS priority,
(80 - ct.soc_pct) * r.battery_capacity_kwh / 100.0
/ (EXTRACT(EPOCH FROM r.departure_time - NOW()) / 3600)
AS required_charge_rate_kw
FROM charger_telemetry ct
JOIN fleet_routes r ON ct.van_id = r.van_id
WHERE ct.soc_pct < 80;| van_id | depot | current_soc | priority | scheduled_start | est_cost | window |
|---|---|---|---|---|---|---|
| EV-0447 | Depot-ATL-07 | 18 | P1_CRITICAL | 2024-03-15T17:42:14.000Z | 14.62 | IMMEDIATE |
| EV-0623 | Depot-DFW-03 | 12 | P1_CRITICAL | 2024-03-15T17:42:14.000Z | 17.89 | IMMEDIATE |
| EV-0558 | Depot-ORD-12 | 37 | P2_URGENT | 2024-03-15T23:00:00.000Z | 4.64 | OFF_PEAK_DEFERRED |
| EV-0312 | Depot-ATL-07 | 71 | P4_DEFERRABLE | 2024-03-15T23:00:00.000Z | 0.97 | OFF_PEAK_DEFERRED |